City hospital, Moscow

ClientNew building of a Moscow city hospital, 65,000 m²
AreasEntrances, blood collection, canteen, café
FabricationKARLSON upholstery factory, Ramenskoye
Timeline32 days from contract to installation
Hospital atrium with sofas and armchairs under a timber slatted ceiling
The brief

More than seventy sofas and a hundred and thirty armchairs for the public areas of a new hospital building, made and installed in 32 days so that the opening date did not move.

Entrance halls, the blood collection area, the canteen and the café each needed their own furniture, and all of it had to meet hospital hygiene rules: surfaces that take disinfectants and no gaps where dust can collect. A volume like this normally takes at least two months, so the factory ran three shifts with no days off.

70+sofas
130armchairs
32 daysfrom contract to full installation
4 floorsfurnished in 4 days
Curved sofa in sage green around a round table in a hospital hall
Pair of curved sofas on timber plinths in a waiting area
Ochre armchairs and a sofa by a window
Grey and ochre armchairs among planters
Curved sofas in the entrance hall
Grey sofas with cushions in a waiting area
What we made

Scope of supply

3- and 4-seat sofas for the entrance hallssteel frame, solid oak trims, faux leather
2-seat sofas and armchairs for blood collectiontilted seat, lumbar support
Corner sofas and banquettes for the canteen and caféfaux leather backs, stain-resistant fabric seats
Light armchairspowder-coated metal legs
Protective wall panels behind the sofasour own suggestion
How we did it

Built for disinfectant, rush hours and a fixed opening date.

All fabrics and leathers carry the certification required for medical institutions and can be washed with standard hospital disinfectants without fading or cracking.

Entrance sofas got extra strength in welds and fixings, because at peak hours more people sit on them than the seat count suggests.

The building was not yet fully commissioned and the goods lifts worked on and off, so the large sofas went up the stairs knocked down and were assembled in the rooms.

We also made and fitted protective panels on the walls behind the sofas in the blood collection area. The hospital later noted this as a useful addition.